June 30 to July 3

Went to visit the block on June 30.  By the time that I got there, the piers had been done.  No rock was hit, and the pier allowance will not be exceeded.  By the time that I left, they were filling the holes with concrete.

July 3.  Was advised that the slab has been poured.  Very happy with how things are going so far.